CONTRACT NUMBER: 7756
CONTRACT: East Washington Avenue Sanitary Sewer Rehab - 2016
Percentage of Contract Completed: 100.0%
Associated Projects:
  • CIPP Rehab of Large Diameter Sanitary and Storm Sewer (10290)
PROJECT: CIPP Rehab of Large Diameter Sanitary and Storm Sewer
Project Number: 10290
Bid Due Date: 06/24/16
Bid Open Date: 06/24/2016
Estimated Start Date: 10/17/2016
Estimated Completion Date: 11/26/2016
Percent of Project Completed: 100.0 %
Contract Amount: $1,407,205.00
Project Contractor: Terra Engineering & Construction Corporation
Construction Year: 2016
Construction Type: Sanitary
District:
PROJECT CONTACT:
Project Manager: Kyle Frank
Phone: 608-266-4098
Email: kfrank@cityofmadison.com
Inspector: Vandenheuvel, Adam
Phone: 264-4126


Documents & Specs