Skip to main content

City of Madison

Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 7895
CONTRACT: Villager Mall Alley and Storm Relief
Percentage of Contract Completed: 96.2%
Associated Projects:
  • Villager Mall Alley and Storm Relief (11491)
PROJECT: Villager Mall Alley and Storm Relief
Project Number: 11491
Bid Due Date: 05/05/17
Bid Open Date: 05/05/2017
Estimated Start Date: 06/21/2017
Estimated Completion Date: 11/03/2017
Percent of Project Completed: 96.2 %
Contract Amount: $1,021,341.29
Project Contractor: CAPITOL UNDERGROUND INC
Construction Year: 2017
Construction Type: Storm
District: 14,
PROJECT CONTACT:
Project Manager: Glen Yoerger
Phone: 608-261-9177
Email: gyoerger@cityofmadison.com
Inspector: Ziegler-Henderson, Lauri
Phone: 261-5585