PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 6559
CONTRACT: Cross Street & Wyota Avenue Storm Sewer - 2010
Percentage of Contract Completed:
96.1%
|
Associated Projects:
- Cross Street & Wyota Avenue Storm Sewer - 2010 (53W1044)
|
| PROJECT: |
Cross Street & Wyota Avenue Storm Sewer - 2010 |
| Project Number: |
53W1044 |
| Bid Due Date: |
12/03/10
|
| Bid Open Date: |
12/10/2010 |
| Estimated Start Date: |
04/18/2011
|
| Estimated Completion Date: |
05/01/2011
|
| Percent of Project Completed: |
96.1 %
|
| Contract Amount: |
$94,919.00
|
| Project Contractor: |
HOMBURG CONTRACTORS INC
|
| Construction Year: |
2010 |
| Construction Type: |
Storm |
| District: |
10,
|
|
PROJECT CONTACT: |
| Design Engineer: |
Max Conway |
| Phone: |
608-261-9127 |
| Email: |
mconway@cityofmadison.com |
| City Construction Engineer: |
John Fahrney |
| Email: |
jfahrney@cityofmadison.com |
| Phone: |
(608) 266 9091 |
| Inspector: |
Mael, Stewart |
| Phone: |
261-9695 |
Documents & Specs
|