CONTRACT NUMBER: 6817
CONTRACT: CIPP Rehab of Sanitary Sewers Phase 2 - 2011
Percentage of Contract Completed: Not Available
Associated Projects:
  • CIPP Rehab of Sanitary Sewers Phase 2 - 2011 (53W1357)
PROJECT: CIPP Rehab of Sanitary Sewers Phase 2 - 2011
Project Number: 53W1357
Bid Due Date: 10/07/11
Bid Open Date: 10/14/2011
Estimated Start Date: 01/05/2012
Estimated Completion Date: 01/04/2013
Percent of Project Completed: Not Available
Contract Amount: $140,653.00
Project Contractor: TERRA ENGINEERING & CONSTRUCTION CORP
Construction Year: 2011
Construction Type: Sanitary
District:
PROJECT CONTACT:
Design Engineer: Farit Torres-Lowe
Phone:
Email:
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Not Available