CONTRACT NUMBER: 7999
CONTRACT: N. Hancock Street Reconstruction
Percentage of Contract Completed: 95.3%
Associated Projects:
  • N. Hancock Street Reconstruction (11469)
PROJECT: N. Hancock Street Reconstruction
Project Number: 11469
Bid Due Date: 10/06/17
Bid Open Date: 10/06/2017
Estimated Start Date: 04/02/2018
Estimated Completion Date: 06/29/2018
Percent of Project Completed: 95.3 %
Contract Amount: $1,411,557.50
Project Contractor: CAPITOL UNDERGROUND INC
Construction Year: 2018
Construction Type: Street
District: 02,
PROJECT CONTACT:
Project Manager: Christy Bachmann
Phone: 608-266-4095
Email: cbachmann@cityofmadison.com
Inspector: Armstrong, Steve
Phone: 266-4914