Skip to main content

City of Madison

Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 8309
CONTRACT: Chip Sealing 2019-East (ald dist 16)
Percentage of Contract Completed: 100.0%
Associated Projects:
  • Pavement Crack Repair and Chip Seal 2019 (11878)
PROJECT: Pavement Crack Repair and Chip Seal 2019
Project Number: 11878
Bid Due Date: 04/11/19
Bid Open Date: 04/11/2019
Estimated Start Date: 05/28/2019
Estimated Completion Date: Not Available
Percent of Project Completed: 100.0 %
Contract Amount: $1,461,948.90
Project Contractor: Fahrner Asphalt Sealers, LLC
Construction Year: 2019
Construction Type: Street
District:
PROJECT CONTACT:
Project Manager: Steve Sonntag
Phone: 608-267-1997
Email: ssonntag@cityofmadison.com
Inspector: Not Available
Phone: Not Available


Documents & Specs