STOUGHTON ROAD PFLAUM BUCKEYE INTERSECTIONS WEEKLY CONSTRUCTION UPDATE FRIDAY, OCTOBER 24TH 2014

October 25, 2014 8:04 AM

STOUGHTON ROAD: PFLAUM & BUCKEYE INTERSECTIONS WEEKLY CONSTRUTION UPDATE – FRIDAY, OCTOBER 24TH, 2014
PROJECT ID: 5410-02-71/72
LOCATION: USH 51 (Stoughton Road) intersection with Pflaum Road and with Buckeye Road
DURATION: August 18th
, 2014 to November 2014
DESCRIPTION:
Major improvements include:
? Traffic signal and signing replacement
? Monotube traffic signal and overhead sign structure installations
? Concrete pavement replacement and repair on Pflaum Road, Buckeye Road, and USH 51
? Concrete island reconstruction
UPCOMING CONSTRUCTION OPERATIONS:
? Completing electrical installations for the new traffic signal system
? Installation of the new permanent signing
? Finishing the concrete sidewalk at Pflaum and Buckeye Road
? Completing the new pavement markings
? Restoration and landscaping
UPCOMING TRAFFIC IMPACTS:
? Pflaum Road & Buckeye Road Lane Restrictions:
o Pflaum Road will remain in the 'Stage 3' traffic configuration until Tuesday. Delays are expected during peak travel
times. Using an alternate route is recommended..
o Buckeye Road traffic patterns will change based on the Contractors' operations. All movements will be maintained.
o Delays are expected on Pflaum & Buckeye during peak travel times
? USH 51 Nighttime Lane Closures (removal of the temporary traffic signals):
o Night of Monday 10/27:
? 7pm – 6am: Northbound USH 51 right lane closure from Pflaum Rd to Buckeye Rd
? 7pm – 6am: Southbound USH 51 right lane closure from Buckeye Rd to Pflaum Rd
o Night of Tuesday 10/28:
? 7pm – 6am: Northbound USH 51 right lane closure from Pflaum Rd to Buckeye Rd
? 7pm – 6am: Southbound USH 51 right lane closure from Buckeye Rd to Pflaum Rd
o Night of Wednesday 10/29:
? 7pm – 6am: Northbound USH 51 left lane closure from Pflaum Rd to Buckeye Rd
? 7pm – 6am: Southbound USH 51 left lane closure from Buckeye Rd to Pflaum Rd
o Night of Thursday 10/30:
? 7pm – 6am: Northbound USH 51 left lane closure from Pflaum Rd to Buckeye Rd
? 7pm – 6am: Southbound USH 51 left lane closure from Buckeye Rd to Pflaum Rd
? Delays are expected on USH 51 during the nighttime lane closures
Note that the anticipated work above is based on the Contractor's current schedule and is subject to change depending on weather
and field conditions encountered. Please take extra caution and slow down when travelling through the work zone.




Email to a friend Email to a friend

Subscribe to Email List

Subscribe to the Alder DeMarb, District 16 email list:


By participating on this list the Wisconsin Public Records Laws may subject your email address to disclosure to third parties. By selecting "Yes" you are requesting that we treat your email address that you have provided to this list as confidential and you are also stating that you would not participate in this service if the City is obligated to release your email address to such third party requesters.


Archive

2017
2016
2015
2014
2013

Labels

Alder DeMarb's Blog
Announcements
Uncategorized