City of Madison Logo
Project Summary

This project extends from Valley View Road to Cross Country Road. This project is scheduled for design from 2011-2015 and construction in 2015-2016. The project includes reconstructing CTH M to divided roadway with a median and curb & gutter.

Current proposed plans can be found here: 

CTH M - Flagstone to Prairie Hill

CTH M - Cross Country to Flagstone

The City of Madison, City of Verona and Dane County held a Public Information Meeting on this project on December 8 2011, 6 PM at the Verona Senior Center, 108 Paoli Street, Verona WI.  Representatives from the City of Madison, City of Verona and Dane County discussed the proposed project and answered questions.  A pdf of the presentation can be found here:    CTH M PIM PowerPoint

A pdf of the handout provided can be found here:  CTH M PIM Handout

The second Public Information Meeting for this project was held May 24th 2012, 6 PM at the Verona Senior Center, 108 Paoli Street, Verona, WI. Representatives from the City of Madison, City of Verona and Dane County discussed the proposed project and answered questions.  A pdf of the presentation can be found here:    CTH M PIM 2 Powerpoint

A pdf of the handout provided can be found here:  CTH M PIM 2 Handout

A third Public Information Meeting for this project was held on March 12, 2014, 6 P.M. at the Verona Senior Center, 108 Paoli Street, Verona, WI.  Representatives from the City of Madison, City of Verona and Dane County discussed the proposed project and answered questions.  A pdf of the presentation can be found here: CTH M PIM 3 Powerpoint