  Work on the project for the week of August 4th, 2014:
 

  • Work on Junction Road includes reconstruction of the medians, electrical, curb and gutter, landscaping and signing
  • Work on Mineral Point Road includes construction of retaining wall at the Beltline, reconstruction of the medians, grading, curb and gutter and electrical
  • Work on the Jug Handle: work on new pedestrian bridges within the Jug Handle, and construction of detention pond

 
 Traffic Impacts
 

  • Monday August 4th, Northbound Junction Road Traffic will be stopped for 5-10 minutes to install an overhead sign bridge between 9am-3pm.
  • Watts Road is reduced to one lane in each direction
  • Eastbound and Westbound Mineral Point Road is 2-lanes
  • South Junction Road is 1-lane in each direction from the Valley View Roundabout to Mineral Point Road and 2-lanes north of Mineral Point Road.
  • Single lane closures are possible between 9:00 AM and 3:00 PM

The project is anticipated to be completed at the end of August.

CTH M Corridor Map

The County Highway M corridor is currently under study with the intent to reconstruct the roadway with an urban cross section, including medians, bike lanes and sidewalks. The corridor contains four individual projects.  Please use the links on the right to get information on the individual projects.