Gregory St., Knickerbocker St., Sprague St., and Sheldon St.

Last Updated: 09/15/2017

Gregory Street, Knickerbocker Street, Sprague Street and Sheldon Street Reconstruction Assessment District - 2017

UPDATE

Week of Work Task

9/4 Curb and driveway work on Knickerbocker and Gregory, speed humps east Gregory
9/11 Continue Curb and driveway work, fine grade for asphalt, landscaping
9/18 Asphalt paving
9/25 final restoration, speed humps on west Gregory
10/1 Asphalt paving

Roads are closed to through traffic.

Project Limits:

Gregory St - Baltzell Street to Sheldon Street
Knickerbocker St - Gregory Street to Monroe Street
Sprague St - Gregory Street to Monroe Street
Sheldon St - Fox Avenue to Sprague Street Project Details:
The project includes replacing cub and gutter, pavement,drive aprons, and spot repairs of the sidewalk. Public utility replacement includes sanitary sewer main and laterals, water main and services, and storm sewer. Multiple trees will be removed for various reasons as part of this project. A summary of the affected trees in the project limits can be found here:
Tree Report


Public Meeting:
A public meeting was held on December 1, 2016. The powerpoint presentation and plan from the meeting can be viewed here:
Presentation
Plan