Renovated Shelter and New Restrooms/Concessions

Following a number of public neighborhood meetings, the decision was made to renovate the existing open-air shelter (removing the current restrooms, benches and knee-wall surrounding the shelter, replacing the roof and concrete slab, adding an ADA ramp and railings, and upgrading the lighting) and to build a new restroom/concession building.  Estimated project cost $950,000.  A separate project to replace and enlarge the parking lot and other sitework improvements will follow.


City User Agency:  Parks Division
Design and Planning: Completing Construction Documents
1st Advertisement of Bid: March 10, 2017
Bid Due Date: April 7, 2017
Construction Start Date: June 1, 2017
Expected Completion Date: May 2018


Penn Park Shelter Renovation
Penn Park Shelter Renovation

Penn Park New Concessions and Restrooms
Penn Park New Concessions and Restrooms


Project History:

Presentations from Public Input Meetings can be found HERE

February 16, 2017  File #46173
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids.