Last Updated: 08/17/2017

N. Sherman Avenue Assessment District-2016

Project is complete.
 
Limits:
Golf Parkway to approximately 1500’ north
 
Schedule:
Early August 2016 til October 2016
 
Details:
Extend water main and sanitary sewer main within the project limits. Install concrete sidewalk on the west side of the street.  Construct a street with 28’ of asphalt, concrete curb and gutter on the west side and a gravel shoulder on the east side of the street.

Plan
plan