Last Updated: 08/17/2017

Turner Avenue, Allis Avenue and Maher Street Assessment District-2016

UPDATE
Project is complete.
 
Limits:
Turner Ave from Kay St to Buckeye Rd, Allis Avenue from Turner Avenue to S. Stoughton Rd Frontage Rd, and Maher Street from Allis Avenue approx. 200’ north.
 
Schedule:
May 30, 2016-late October, 2016
 
Details:
The sanitary sewer main and laterals and the water main will be replace within the project limits.  Storm sewer will be installed to convey storm water to the existing storm sewer system.  Concrete sidewalk will be constructed on Turner Avenue and Allis Avenue.  Concrete curb and gutter and an asphalt pavement will be constructed.  The three streets will be 32’ wide.
 
Plan:
plan
 
Public Informational Meeting
A public informational meeting was  held on January 27, 2016
Handout