University Avenue
April 21, 2024 Update
Work the Week of April 22, 2024
The contractor will complete installation of stamped and colored concrete medians and will begin final restoration and placement of sod in the medians of University Ave. and Campus Dr. throughout the project limits. This work will require daily off-peak (9 AM – 3 PM) single-lane closures in both the eastbound and westbound directions on University Ave. and Campus Dr.
Roadway grading and preparation for concrete curb and sidewalk on Franklin Ave. and Schmitt Pl. will be occurring during the week. Traffic on Franklin Ave. will be maintained while this work is being completed.
Installation of traffic signal bases and poles will continue in the University Ave. medians.
Temporary asphalt pavement along the median curb and left-turn lanes on University Ave. will be removed and existing roadway aggregates will be final graded in preparation for placement of permanent asphalt pavement.
Work the Week of April 29, 2024
The contractor will complete median work throughout the project limits.
Backfilling of median curb and gutter and placement of topsoil and sod in the medians will be completed.
Asphalt paving along the recently placed median curb will occur along with the installation of lower and middle layers of permanent asphalt pavement for left-turn lanes along University Ave. Please note that the asphalt paving operations will likely require daily off-peak (9 AM – 3 PM) single-lane closures in both the eastbound and westbound directions on University Ave. and Campus Dr.
Traffic/Pedestrian/Bike Impacts
Traffic will remain in a configuration that maintains two lanes in both directions during peak travel periods on University Ave. within the project limits (from approximately Shorewood Blvd. to University Bay Dr.). Through traffic is being maintained on side streets; however, alternative routes should be used when possible. Short-term sidewalk detours on the south side of University Ave. between Ridge St. and Farley Ave. will be needed to complete the remaining sidewalk and pedestrian ramps. Please be alert for sidewalk closed and pedestrian detour signage that will be in place while this work is being completed. Also note that the Bus Rapid Transit (BRT) project has long-term single-lane closures on eastbound Campus Dr. east of the Highland Overpass. additional information on work related to the BRT project can be found here: https://www.cityofmadison.com/metro/routes-schedules/bus-rapid-transitNote that the work is weather dependent and may be subject to change.
View the full University Avenue Weekly Update.
View past project updates »Project Details
Project Information
Project Overview
University Ave is scheduled for reconstruction from Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave. The City of Madison is jointly participating with the Village of Shorewood Hills on the design and construction. The project includes reconstruction of pavement, curb and gutter, sidewalk as necessary, street lighting, traffic signals, water main, sanitary sewer and storm sewer. Alternatives to improve pedestrian & bicycle connectivity, bus rapid transit initiatives and stormwater drainage have been reviewed, and the project plans have been updated to include a new pedestrian & bike overpass of University Bay Dr., a widened sidewalk along the southerly side of University Ave., and a 96-inch storm sewer pipe to help improve drainage in the area. The project continues to be coordinated with the City’s planning efforts for bus rapid transit.
Full Project Map
Typical Section Example
University Bay Overpass Alternative
Project Fact and Details Sheet
View a larger image of proposed improvements
Project Limits
Shorewood Boulevard/Hill St to University Bay Drive/Farley Ave.
Project Schedule
Construction is scheduled for 2022.
Public Involvement
There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates and times are indicated below:
Public Information Meetings
- March 11, 2021 Public Information Meeting PowerPoint Presentation
- March 11, 2021 Public Information Meeting Recording
- Univ Ave (Shore-Univ Bay Dr) Roll Plot Exhibit
- Dec. 18, 2019 Public Information Meeting PowerPoint Presentation
- Dec. 18, 2019 Public Information Meeting Display Photo
- June 13, 2019 Public Information Meeting PowerPoint Presentation
- June 13, 2019 Public Information Meeting Preliminary Plan Overview
- The residents and businesses impacted by the University Avenue project are welcome to attend a monthly coordination meeting to discuss the University Avenue construction project. The coordination meeting will be held on the second Wednesday of each month at 11 a.m., 3230 University Avenue, Suite No. 7. The first meeting was held June 8, 2022. Integrity Grading and Excavating will give a construction schedule update at each meeting followed by an open platform for any questions and/or concerns with the ongoing construction operations.
City Meetings, Process
Board of Public Works: June 16, 2021
Transportation Commission: April 15, 2020
Common Council: July 6, 2021
Mailings
Extension of work hours for Construction Activities (Starting around Aug. 15, 2022)