Last Updated: 03/08/2017

UPDATE 3/8/17 - Second Public Information Meeting scheduled. See details below.

Project Description:

This project will involve the replacement of pavement, city utilities, curb and gutter, and sidewalk on West Wilson Street from Martin Luther King Junior Blvd. to South Henry Street. The City is currently exploring options for incorporating improved bicycle facilities into the project.

Project Schedule:

The project is expected to last approximately 3 months beginning early August and running through early November.
The City may bid the project in a way that gives the contractor the option to do the work either in the fall of 2017 or spring of 2018.

Public Information Meeting:

A second Public Information Meeting is scheduled for Monday, March 20 at 6:30 PM in Room 351 of the City-County Building. The notice that was sent to owners, residents, and businesses for this meeting can be found here:
PIM Number 2 Notice

A Public Information Meeting was held on Tuesday February 21, 2017.  The presentation and plans can be found below.  At this meeting, the project was presented with a proposed widened sidewalk on the south side while maintaining the existing travel and parking lanes.
Presentation
Plans

The project was presented to the Pedestrian, Bicycle, and Motor Vehicle Commission on February 22, 2017, and the commission requested that additional input be gathered on the project.

Another public informational meeting is being held on Monday, March 20, 2017 at 6:30 PM in Room 351 of the City County Building (210 Martin Luther King Junior Blvd.).  Additional options will be presented at this meeting including the original proposal ( widened sidewalk on the south side), a option with a dedicated counter-flow bike lane adjacent to the sidewalk, and an option with a separate contra-flow bike lane on or off the street, which would result in the loss of parking.