Fire Station 4 Lighting Retrofit

March 29, 2024 Update

This project has been completed.

View past project updates »

Project Details

  • Location

    • 1437 Monroe St.
      Madison, WI 53711
  • Project Type

  • Status

    Completed
  • Estimated Schedule

  • Alder District

    District 5
  • Contract Number

Project Information

Latest Update

October 02, 2023
Material has arrived and construction has started on-site.

Project Overview

Replace old lighting fixtures and controls with modern LED lighting.

Project Schedule

City User Agency: City of Madison Fire Department

1st Advertisement of Bid: April 13, 2023 available only on Bid Express
Pre-Bid Building/Site Contractor Meeting: April 26, 2023 @ 11:00 a.m. at the project site located at 1437 Monroe St., Madison, WI
Bid Due Date: May 04, 2023
Construction Start Date: July 2023
Expected Completion Date: January 2024

"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."

Public Involvement

There are a number of points of contact during this project where the public is encouraged to give feedback as part of public information meetings and public hearings. Dates, times and locations are indicated below:

City Process Meetings

June 06, 2023 Common Council File #77795
May 17, 2023 Board of Public Works File #77795
Awarding Public Works Contract No. 9320, Fire Station 4 Lighting Retrofit

Feb. 07, 2023 Common Council File #75537
Jan. 18, 2023 Board of Public Works File #75537
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Fire Station 4 Lighting Retrofit           


 

 

Project Updates

This project has been completed.

Was this page helpful to you?