Closure of Langdon Street at N. Henry Street, starting 8/5/13

August 2, 2013

The City and its contractors are currently reconstructing 500 and 600 blocks of North Henry Street. The project consists of the installation of underground utilities, replacement of concrete sidewalk, curb and gutter, drive aprons and new asphalt pavement.

To facilitate the underground utility construction, Langdon Street will be closed at North Henry Street from Monday, August 5th, to Friday, August 9th.

Access to all properties will be maintained. Sidewalk on at least one side of the street will be open at all times.

Motorists are encouraged to use alternative routes to avoid delay during this project.

# # # # # #

__________________________________________________
David C. Dryer, P.E., City Traffic Engineer and Parking Manager

Contact:
  • Yang Tao, City Traffic Engineering, 608-266-4815
  • John Fahrney, City Construction Engineer, 608-266-4862
  • Jim Davis, Speedway Sand & Gravel, Inc, 608-575-9576