2018 East Parks Division Fencing and Backstops - RFB 4738-0-2018

Last Updated: 11/05/2018

Aldo Leopold backstop

The new backstop at Aldo Leopold Park, 10-19-2018

Contractor Century Fence Company, who submitted the low bid of $32,807.00 in response to the Request for Bids (RFB 4738-0-2018) Parks issued earlier this summer through City of Madison Purchasing completed work under the project the week of October 24th. 

Improvements to central and east park sites under this contract include:

  • Aldo Leopold Park - backstop replacement - complete
  • Orton Park - backstop replacement - complete and replacement of fencing adjacent to the basketball court - complete
  • Heritage Sanctuary - new fencing and replacement of portions of existing chain link fencing at 'gateway' area - complete
  • Reynolds Park - backstop replacement - complete

Please contact Landscape Architect Kate Kane at (608) 261-9671 or kkane@cityofmadison.com if you have any questions about the project.