2018 Parks Division West Fencing and Backstops - Contract: 8174 2018 Parks Division West Fencing and Backstops

Last Updated: 06/21/2018

Work is nearly complete to replace fencing, including backstops, at several west park properties!

Contractor Century Fence Company, who submitted the low bid of $44,556.00 at the bid opening in April, began work on the contract in early June and is anticipated to be done at all sites by early July. The work schedule submitted by the Contractor is as follows:

  • Bordner Park - backstop replacement and repair to tennis court fencing* on 6/15/2018 and completed on or before 6/22/2018.
  • Garner Park - new divider fencing at pickleball courts* on 6/11/2018 and completed on or before 6/13/2018.
  • Rennebohm Park - backstop removal and replacement on 6/5/2018 and completed by 6/8/2018.
  • Wingra Park - backstop repair on 6/6/2018 and completed by 6/8/2018.


*Please note that closure of the tennis and pickleball court facilities will be required while work is occuring. 
Please contact Landscape Architect Kate Kane at (608) 261-9671 or kkane@cityofmadison.com if you have any questions about the project.