Dudgeon School Park Playground Replacement - Contract: 2018 Playground Replacements Group 1 (8154)

Last Updated: 02/22/2018

The contract to construct the playground improvements at Dudgeon School Park is anticipated to be bid beginning on 3/1, with an anticipated opening on 3/15.  Pending a successful bid opening, the project will start on or before 5/14/2018 at Odana Hills Park, the first project of the group to be started.  Work will begin at Dudgeon School Park shortly thereafter.  All sites within the contract are anticipated to be completed in early August 2018.

You are invited to provide comments or input on the proposed project. If you have questions or comments, please contact Kate Kane at (608) 261-9671 or at kkane@cityofmadison.com.