PUBLIC WORKS CONTRACTS
CONTRACT NUMBER: 7188
CONTRACT: Booster Station 115 Pipeline Improvements
Percentage of Contract Completed:
Not Available
|
Associated Projects:
- Booster Station 115 Pipeline Improvements (53W1693)
|
| PROJECT: |
Booster Station 115 Pipeline Improvements |
| Project Number: |
53W1693 |
| Bid Due Date: |
01/09/15
|
| Bid Open Date: |
01/09/2015 |
| Estimated Start Date: |
04/02/2015
|
| Estimated Completion Date: |
07/31/2015
|
| Percent of Project Completed: |
Not Available
|
| Contract Amount: |
$1,441,208.43
|
| Project Contractor: |
SPEEDWAY SAND & GRAVEL INC
|
| Construction Year: |
2014 |
| Construction Type: |
Misc |
| District: |
17,
|
|
PROJECT CONTACT: |
| Project Manager: |
Kelly Miess |
| Phone: |
261-9640 |
| Email: |
kmiess@madisonwater.org |
| Inspector: |
Jeff Belshaw |
| Phone: |
608-267-1166 |
Documents & Specs
|