Project Summary

This intersection project, involving the City of Madison, Dane County, and Wisconsin Department of Transportation, is proposed to address growing traffic congestion, pedestrian, bicycle, and transit infrastructure shortcomings, and future growth. The construction is planned to begin in the fall of 2012.

An Environmental Assessment Report has been prepared for this project.  It is available for download at: M & S EA Report.  A copy of the FONSI (Finding Of No Significant Impact) document is available here:  FONSI.

A preconstruction public information meeting was held on June 14th, 2012 at the Wisconsin Community Bank (8240 Mineral Point Road) regarding this project.  City staff and their consultant discussed the project and construction schedule.  A pdf of the presentation and handout provide are available for download here:

Presentation:  Madison MS Presentation 06-14-12.pdf

Handout:  CTH MS_PIM Handout 06_14_12

View from Mineral Point looking westView from Mineral Point looking east

                                 View larger pdf                                                               View larger pdf

 

Plan

The current plan includes an at-grade intersection for North-bound CTH M/Junction Road and Mineral Point Road, and a split grade intersection for South-bound CTH M/Junction Road and Mineral Point Road. A seperate set of lanes are provided on a jug handle for the South-bound moving vehicles on CTH M/Junction Road to make turning movements on Mineral Point Road.

The proposed schedule is to begin work on grading in the fall of 2012.  Work on the bridge and surrounding roadways would begin in early spring of 2013 and last through the summer of 2014.

A pdf of the current plans are available for download here:

Mineral Point Road (Pleasant View Road to Beltline):  MP - PV to Beltline

Junction Road / South Junction Road (Isaac Dr to south of Watts Rd):  JR - Isaac to S of Watts

South Junction Road (south of Watts Rd):  JR - S of Watts

Construction

The Mineral Point Road & Junction Road project has begun and is expected to last until July 31, 2014.  Mineral Point Road will be reconstructed from Pleasant View Road to the Beltline.  Junction Road will be reconstructed from Isaac Drive to Valley View Road.  A bridge will be constructed to carry traffic southbound on Junction Road over Mineral Point Road.

Detailed construction plans can be viewed here:

construction plan  (large file - 141 MB)

A Traffic Management Plan has been created for this project.  The document is available for download here:  08_17_2012 TMP MS Final

Meetings for businesses or residents will be held bi-weekly at the job trailer for the project.  The job trailer is located on the south side of Mineral Point Road approximately 500' west of Junction Road.  The meetings will be held on the 1st and 3rd Tuesdays of the month at 2:30 pm starting on June 4, 2013.

A graphic which shows the correct turning maneuvers for each direction is included here:  intersection turning movements