Gregory St., Knickerbocker St., Sprague St., and Sheldon St.

Last Updated: 08/17/2017

Gregory Street, Knickerbocker Street, Sprague Street and Sheldon Street Reconstruction Assessment District - 2017

UPDATE

Week of Work Task
8/14 storm sewer on Knickerbocker
8/21 storm on Gregory, street grading on Knickerbocker
8/28 finish storm on Gregory, finish street grading on Gregory
9/4 Curb and driveway work on Knickerbocker and Gregory, speed humps east Gregory
9/11 fine grade for asphalt, landscaping
9/18 Asphalt paving
9/25 final restoration, speed humps on west Gregory
10/1 Asphalt paving

Project Limits:

Gregory St - Baltzell Street to Sheldon Street
Knickerbocker St - Gregory Street to Monroe Street
Sprague St - Gregory Street to Monroe Street
Sheldon St - Fox Avenue to Sprague Street Project Details:
The project includes replacing cub and gutter, pavement,drive aprons, and spot repairs of the sidewalk. Public utility replacement includes sanitary sewer main and laterals, water main and services, and storm sewer. Multiple trees will be removed for various reasons as part of this project. A summary of the affected trees in the project limits can be found here:
Tree Report


Public Meeting:
A public meeting was held on December 1, 2016. The powerpoint presentation and plan from the meeting can be viewed here:
Presentation
Plan