Metro Transit Phase 2 – HVAC Replacement

Last Updated: 03/07/2019

Project Scope

This project will provide new HVAC systems throughout the facility which will address zoning, pressurization and ventilation issues in the facility. Budget is $7M.

This is the second phase of a 6-phase construction project (totaling $50M+). Over the next 5 years the capital improvement plan for this facility is to design and bid a project each year in the $7-12M range:

  • 2019 Construction: Phase 1 is the addition of a new service lane addition, totaling ~$6.5M
  • 2020 Construction: Phase 2 is replacement of HVAC, totaling ~$7M
  • 2021 Construction: Phase 3 is remodeling of maintenance bays, including lift replacements, totaling ~$12M
  • 2022 Construction: Phase 4 is remodeling of Admin/Dispatch areas, including new electrical service, totaling ~$9.5M
  • 2023 Construction: Phase 5 is remodeling of bus storage areas, including new lighting and fire suppression, totaling ~$7M

2024 Construction: Phase 6 is exterior improvements, including tuckpointing, metal panels, skylights and sawtooth roof replacement, totaling ~$10M


City User Agency: Metro Transit

Design and Planning: April 2019 through December 2019
1st Advertisement of Bid: January 2020
Bid Due Date: February 2020
Construction Start Date: March 2020
Expected Completion Date: December 2020


Project History

April 17, 2018 File #50922
Resolution authorizing a non-competitive purchase of services contract with Mead and Hunt for professional architectural and engineering services for the design of (2019 - Phase 1) Metro Bus Barn Facility Upgrades.