Project Description
This project will remove and replace concrete curb and gutter; remove and replace sidewalk, as needed; remove and replace drive aprons, install a new asphalt pavement; replace sanitary sewer main and laterals; replace the water main; replace or extend storm sewer, as necessary.

Project Limits
E Washington Avenue to E Johnson Street

Project Schedule
July 27, 2017 - Public Information Meeting
August 23, 2017 - Board of Public Works
September 5, 2017 - Common Council
April 2, 2018 - Begin Construction

Public Information Meeting
A Public Information Meeting was held on July 27, 2017. The plan from this meeting can be found here: PIM Display