Last Updated: 10/06/2017

Construction Update
Contractor is working on water main in multiple locations.

Contractor plans to complete the project this year.  If they can't, the roads will have asphalt surface for the winter.

Project Description
This project will construct curb on Remington Rd and the S Stoughton Rd Service Road and construct a new pavement.  It will also resurface the existing pavement on Blossom Ln.  Existing sanitary sewer mains and laterals and water main will be replaced.

Project Limits
S Stoughton Rd Service Rd - Remington Rd to north end
Blossom Ln - Stoughton Rd Service Rd to Remington Rd
Remington Rd - Stoughton Rd to east end