Last Updated: 07/07/2021

July 07, 2021 Update:

Bid Due Date extended: August 19, 2021
Construction Start Date: October 11, 2021

Expected Completion Date: September 30, 2022
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."


Solar Electric Installation

Installation of a roughly 60 kW solar photovoltaic system at the Madison Police Department Training Center. The system will be a combination of roof mounted and ground mounted modules and will produce an estimated 78,000 kWh per year. When combined with the building’s existing roof mounted system, 35% of the building’s electricity usage will be generated by the solar arrays.


City User Agency: Madison Police Dept.
Project Status: BIDDING!  Available only on BID EXPRESS
Planning and Design: Jan – May 2021
1st Advertisement of Bid: June 10, 2021
Bid Due Date: August 19, 2021
Construction Start Date: October 11, 2021

Expected Completion Date: September 30, 2022
"All information regarding dates/times/locations are informational and should be verified with official bidding documents posted on Bid Express."


Project History

June 02, 2021 File #65670
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Solar PV - MPD Training & MPD East.