Last Updated: 05/27/2016

WEEKLY UPDATE
  
University Ave & W. Gorham St (Broom – Frances):   Contractor is replacing the concrete pavement that was removed for installing new utilities.  Expected completion is June 3.

University Ave & W. Gorham St (Broom – Frances):  Construction is scheduled April 23 – June 3.  The project includes installing sanitary sewer, water services and electric services for a new apartment building.
 
University Avenue/Gorham St will remain open to traffic.  However, one lane will be closed at all times.  During non peak hours (9 am – 3 pm) and Saturdays two lanes may be closed.