Project Description:
 
E Dayton Street( N Blount St – N Livingston St)
The project consists of replacing curb & gutter, Pavement, drive aprons and spot repairs of the sidewalk.  Utility replacement including Sanitary sewer and laterals, water main and services and storm sewer.
 
N Butler St and N Hamilton St ( E Johnson St – E Gorham St)
The project consists of new asphalt pavement and spot replacement of : curb & gutter, drive aprons  and sidewalks. Utility replacement including Sanitary sewer and laterals, water main and services and storm sewer.
 
S Blount St(E main St – Williamson St)
The project consists of new asphalt pavement with spot replacement of : curb & gutter, drive aprons  and sidewalks.  Utility replacement including Sanitary sewer and laterals, water main and services and storm sewer.

Project Schedule:

Construction is scheduled for summer of 2017(Mid May – August)