Last Updated: 08/17/2017

UPDATE

Butler:  Contractor plans to start replacing the water main on 8/21
Hamilton:  Contractor plans to start working on storm structures on 8/28
Blount:  Contractor plans to start replacing the sanitary sewer on 8/21

Project Description:
N Butler St and N Hamilton St ( E Johnson St – E Gorham St)
The project consists of new asphalt pavement and spot replacement of : curb & gutter, drive aprons  and sidewalks. Utility replacement including Sanitary sewer and laterals, water main and services and storm sewer.
 
S Blount St(E main St – Williamson St)
The project consists of new asphalt pavement with spot replacement of : curb & gutter, drive aprons  and sidewalks.  Utility replacement including Sanitary sewer and laterals, water main and services and storm sewer.

Project Schedule:

Construction is scheduled for summer of 2017(End of August - Mid October)