2018 Tennis and Basketball Court Resurfacings - Contract: 2018 Tennis and Basketball Court Resurfacings

Last Updated: 08/13/2018

Work is currently underway on the contract to perform sport court crack sealing, seal coating and striping at several city park properties!
Fahrner Asphalt Sealers LLC, working with subcontractor Midwest Sealcoat will be at the various sites throughout the month of August and into mid-September.
Work on the contract is anticipated to be completed on or before 9/15/2018.

Westhaven 8.13.2018
Flood test results at Westhaven Trails Park prior to crack filling and resurfacing  (photograph from 8.13.2018)

Projects at eight parks are included in the 2018 contract:

  • Garner Park basketball court striping (through Change Order) - completed week of 8/6/2018
  • Goodman Park - basketball court crack sealing, seal coating and striping - flood test anticipated 8/14/2018
  • Nakoma Park - tennis & pickleball court striping - pickleball striping was contributed by the neighborhood association through funds held by Madison Parks Foundation
  • Odana Hills East Park - tennis court crack sealing, seal coating and striping - date TBD (before 9/15/2018)
  • Olbrich Park - tennis court crack sealing, seal coating and striping - flood test is anticipated for 8/14/2018
  • Rennebohm Park - tennis court crack sealing and striping - completed week of 8/6/2018
  • Richmond Hill Park - basketball court striping - completed week of 8/6/2018
  • Walnut Grove Park - tennis court crack sealing, seal coating and striping
  • Westhaven Trails Park - tennis court crack sealing, seal coating and striping - flood test 8/13/2018; crack filling and sealing week of 8/13/2018