2018 Tennis and Basketball Court Resurfacings - Contract: 2018 Tennis and Basketball Court Resurfacings

Last Updated: 09/13/2018

Work is complete on the contract to perform sport court crack sealing, seal coating and striping at several city park properties!
Fahrner Asphalt Sealers LLC, working with subcontractor Midwest Sealcoat has been at the various sites throughout the month of August and completed work at the final sites on 9/10/2018.

Westhaven 8.13.2018

Flood test results at Westhaven Trails Park prior to crack filling and resurfacing  (photograph from 8.13.2018)

westhave

Courts at Westhaven Trails after work completed 9.7.2018


Projects at eight parks are included in the 2018 contract:

  • Garner Park basketball court striping (through Change Order) - completed week of 8/6/2018
  • Goodman Park - basketball court crack sealing, seal coating and striping - completed on 8/22/2018
  • Nakoma Park - tennis & pickleball court striping - completed week of 8/6/2018; pickleball striping was contributed by the neighborhood association through funds held by Madison Parks Foundation
  • Odana Hills East Park - tennis court crack sealing, seal coating and striping - completed week of 9/10/2018
  • Olbrich Park - tennis court crack sealing, seal coating and striping - flood test & crack filling completed; color coat & striping - completed 9/8 & 9/9
  • Rennebohm Park - tennis court crack sealing and striping - completed week of 8/6/2018
  • Richmond Hill Park - basketball court striping - completed week of 8/27/2018
  • Walnut Grove Park - tennis court crack sealing, seal coating and striping - completed week of 9/5/2018
  • Westhaven Trails Park - tennis court crack sealing, seal coating and striping - flood test 8/13/2018; crack filling and sealing - completed week of 9/5/2018