Portland Park Basketball Court Replacement

Last Updated: 09/25/2020

City Parks Division is reconstructing the basketball court at Portland Park in 2020. The existing court was in poor condition, contained cracking asphalt, and was showing signs of deterioration. 

A new master plan was approved for Portland Park in 2019 which included a slightly revised location for the basketball court and the addition of a Gaga ball area.

 

The project consists of the following:

  • Removal of the existing basketball court and standards
  • Restoration of the existing court area to turf
  • Installation of a new standard half court basketball area and gaga ball area
  • Striping of the new court to half court standards
  • Installation of a new asphalt path spur to serve the court

 

Work is scheduled to be complete by end of 2020.

A schematic of the proposed improvements is shown below in the revised master plan document.

 

If you have questions or comments please contact Corey Stelljes at (608) 266-6518 or cstelljes@cityofmadison.com.

 