| Welcome.
The Mid-State Street Parking & Mixed Use Facility site, as it
progresses, shall focus on the redevelopment of the Buckeye Lot as
a mixed-use project including parking available to the public,
commercial, and residential development. The goal of the mixed-use
project is to support the continued revitalization of the
Mid-State Street area.
|
|
NOVEMBER 14: 2005:
JUNE 20, 2005:
APRIL 18, 2005:
APRIL 8, 2005:
MARCH 28, 2005:
FEBRUARY 21, 2005:
JANUARY 31, 2005:
JANUARY 12, 2005:
Back
to top
DECEMBER
6, 2004:
AUGUST
23, 2004:
Back
to top
|
 |
Please
continue to check back at www.BuckeyeLot.org
to see the progression of the project. |
|
 |
|
The following
is the schedule for this RFP:
-
RFP Issued: August 12, 2004
-
Pre-Submission
Meeting: September 15, 2004
-
Proposal
Submissions Deadline: November 15, 2004
-
Proposal
Reviews: Mid-November – Mid-December 2004
-
Common
Council Selects Developer Team: January / February 2005
The
following is the proposed tentative schedule for the City’s
parking ramp:
-
Issue
RFP for Architectural and Engineering Design Services for the
Mid-State Street Ramp:
November 5, 2004
-
Receipt
of proposals for Mid-State Street Ramp:
December 3, 2004
-
Common
Council Authorizes the Contract for Design Services: February
1, 2005
-
Begin
Design for Mid-State Street Ramp: February 21, 2005
-
Adoption
of a Relocation Order for the Land Acquisition for the
Mid-State Street Parking Ramp: April 19, 2005
-
Advertisement
for Bid for Mid-State Street Parking Ramp: January 6 - 27,
2006
-
Common
Council Awards Mid-State Street Ramp Construction: February
21, 2006
Back