CONTRACT NUMBER: 7158
CONTRACT: CIPP Rehab of Sanitary and Storm Sewers 2013 - Phase 1
Percentage of Contract Completed: Not Available
Associated Projects:
  • CIPP Rehab of Sanitary and Storm Sewers 2013 - Phase 1 (53W1644)
PROJECT: CIPP Rehab of Sanitary and Storm Sewers 2013 - Phase 1
Project Number: 53W1644
Bid Due Date: 08/23/13
Bid Open Date: 08/23/2013
Estimated Start Date: 10/14/2013
Estimated Completion Date: Not Available
Percent of Project Completed: Not Available
Contract Amount: $502,043.00
Project Contractor: TERRA ENGINEERING & CONSTRUCTION CORP
Construction Year: 2013
Construction Type:
District:
PROJECT CONTACT:
Design Engineer: Nathan Wells
Phone: 608-261-9996
Email: nwells@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Not Available
Phone: Not Available