City of Madison

Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 7311
CONTRACT: CCB City Channel and Shared Resource Planning Remodel
Percentage of Contract Completed: 100.0%
Associated Projects:
  • CCB City Channel and Shared Resource Planning Remodel (53W1756)
PROJECT: CCB City Channel and Shared Resource Planning Remodel
Project Number: 53W1756
Bid Due Date: 09/11/15
Bid Open Date: 09/11/2015
Estimated Start Date: Not Available
Estimated Completion Date: Not Available
Percent of Project Completed: 100.0 %
Contract Amount: $893,000.00
Project Contractor: JH FINDORFF & SON INC
Construction Year: 2014
Construction Type: Facilities
District:
PROJECT CONTACT:
Project Manager: Jim Whitney
Phone: 608-266-4563
Email: jwhitney@cityofmadison.com
Inspector: Not Available
Phone: Not Available


Documents & Specs