CONTRACT NUMBER: 7437
CONTRACT: Utilities with Resurfacing 2015
Percentage of Contract Completed: 94.1%
Associated Projects:
  • Utilities with Resurfacing 2015 (53W1793)
PROJECT: Utilities with Resurfacing 2015
Project Number: 53W1793
Bid Due Date: 04/01/15
Bid Open Date: 04/01/2015
Estimated Start Date: 05/20/2015
Estimated Completion Date: 09/04/2015
Percent of Project Completed: 94.1 %
Contract Amount: $2,230,847.05
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2015
Construction Type: Street
District: 05, 11, 20,
PROJECT CONTACT:
Project Manager: Steve Sonntag
Phone: 608-267-1997
Email: ssonntag@cityofmadison.com
Inspector: Mael, Stewart
Phone: 261-9695