PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 7450
CONTRACT: Darbo Drive to Webb Avenue New Street Connection Assessment District - 2018 (Richard Davis Lane)
Percentage of Contract Completed: 96.33%
Associated Projects:
  • Darbo Drive to Webb Avenue New Street Connection Assessment District - 2018 (Richard Davis Lane) (53W1867)
PROJECT: Darbo Drive to Webb Avenue New Street Connection Assessment District - 2018 (Richard Davis Lane)
Project Number: 53W1867
Bid Due Date: 05/24/18
Bid Open Date: 05/24/2018
Estimated Start Date: 12/17/2018
Estimated Completion Date: 11/10/2018
Percent of Project Completed: 96.33 %
Contract Amount: $974,989.32
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2018
Construction Type: Street
District: 06,
PROJECT CONTACT:
Project Manager: Andy Zwieg
Phone: 608-266-9219
Email: azwieg@cityofmadison.com
Inspector: Lauby, Paul
Phone:


Documents & Specs