City of Madison Logo
Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 6935
CONTRACT: Sauk Creek Sewer Access Road, Phase 2
Percentage of Contract Completed: 92.6%
Associated Projects:
  • Sauk Creek Sewer Access Road, Phase 2 (53W1116)
PROJECT: Sauk Creek Sewer Access Road, Phase 2
Project Number: 53W1116
Bid Due Date: 08/24/12
Bid Open Date: 08/31/2012
Estimated Start Date: 10/18/2012
Estimated Completion Date: 11/30/2012
Percent of Project Completed: 92.6 %
Contract Amount: $134,717.40
Project Contractor: DANE COUNTY CONTRACTING LLC
Construction Year: 2011
Construction Type: Sanitary
District:
PROJECT CONTACT:
Design Engineer: Sally Swenson
Phone: 608-266-4862
Email: sswenson@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Mael, Stewart
Phone: 261-9695


Documents & Specs