CONTRACT NUMBER: 7478
CONTRACT: Forest Hill Cemetery- John Catlin Chapel Roof Replacement
Percentage of Contract Completed: 100.0%
Associated Projects:
  • Forest Hill Cemetery- John Catlin Chapel Roof Replacement (53W1922)
PROJECT: Forest Hill Cemetery- John Catlin Chapel Roof Replacement
Project Number: 53W1922
Bid Due Date: 04/24/15
Bid Open Date: 04/24/2015
Estimated Start Date: 06/08/2015
Estimated Completion Date: 10/31/2015
Percent of Project Completed: 100.0 %
Contract Amount: $95,457.00
Project Contractor: MILLEN ROOFING CORP
Construction Year: 2015
Construction Type: Facilities
District: 13,
PROJECT CONTACT:
Project Manager: Paul Stauffer
Phone: 608-266-4366
Email: pstauffer@cityofmadison.com
Inspector: Not Available
Phone: Not Available