CONTRACT NUMBER: 6333
CONTRACT: Tenney Lagoon Outlet Structure Project
Percentage of Contract Completed: 86.1%
Associated Projects:
  • Tenney Lagoon Outlet Structure (53W0732)
PROJECT: Tenney Lagoon Outlet Structure
Project Number: 53W0732
Bid Due Date: 07/08/11
Bid Open Date: 07/15/2011
Estimated Start Date: 09/19/2011
Estimated Completion Date: 11/07/2011
Percent of Project Completed: 86.1 %
Contract Amount: $179,500.00
Project Contractor: TERRA ENGINEERING & CONSTRUCTION CORP
Construction Year: 2009
Construction Type: Storm
District: 02,
PROJECT CONTACT:
Design Engineer: Sally Swenson
Phone: 608-266-4862
Email: sswenson@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Lauby, Paul
Phone: 261-9678