City of Madison Logo
Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 6544
CONTRACT: Sycamore Drains - 4602 Sycamore Avenue
Percentage of Contract Completed: 100.0%
Associated Projects:
  • Sycamore Drains (53W1081)
PROJECT: Sycamore Drains
Project Number: 53W1081
Bid Due Date: 05/27/11
Bid Open Date: 06/03/2011
Estimated Start Date: 07/18/2011
Estimated Completion Date: Not Available
Percent of Project Completed: 100.0 %
Contract Amount: $49,794.00
Project Contractor: JOE DANIELS CONSTRUCTION CO INC
Construction Year: 2010
Construction Type:
District:
PROJECT CONTACT:
Design Engineer: Randy Wiesner
Phone: 608-267-8679
Email: rwiesner@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Not Available
Phone: Not Available


Documents & Specs