CONTRACT NUMBER: 6572
CONTRACT: Joylynne Dr. & Douglas Trl. Assessment Dist. 2010; Turner Ave. Sidewalk Assessment Dist. 2010
Percentage of Contract Completed: 96.7%
Associated Projects:
  • Joylynne Drive and Douglas Trail (53W1068)
PROJECT: Joylynne Drive and Douglas Trail
Project Number: 53W1068
Bid Due Date: 03/04/11
Bid Open Date: 03/11/2011
Estimated Start Date: 05/23/2011
Estimated Completion Date: 08/30/2011
Percent of Project Completed: 96.7 %
Contract Amount: $1,382,813.06
Project Contractor: CAPITOL UNDERGROUND INC
Construction Year: 2011
Construction Type:
District:
PROJECT CONTACT:
Design Engineer: LeAnne Hannan
Phone: 608-266-4057
Email: lhannan@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Hoel, Eric
Phone: 261-9270


Documents & Specs