CONTRACT NUMBER: 6577
CONTRACT: North Frances St. (Langdon St. - North) Assessment District - 2011
Percentage of Contract Completed: 97.4%
Associated Projects:
  • N. Frances Street Reconstruction (53W1125)
PROJECT: N. Frances Street Reconstruction
Project Number: 53W1125
Bid Due Date: 12/09/11
Bid Open Date: 12/16/2011
Estimated Start Date: 05/21/2012
Estimated Completion Date: 07/21/2012
Percent of Project Completed: 97.4 %
Contract Amount: $395,303.10
Project Contractor: RG HUSTON COMPANY INC
Construction Year: 2012
Construction Type:
District:
PROJECT CONTACT:
Design Engineer: Eric Dundee
Phone: 608-266-4913
Email: edundee@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Ziegler-Henderson, Lauri
Phone: 261-5585