CONTRACT NUMBER: 6607
CONTRACT: Utility Replacement with Resurfacing Assessment District - 2011
Percentage of Contract Completed: 97.1%
Associated Projects:
  • Utility Replacement with Resurfacing - 2011 (53W1086)
PROJECT: Utility Replacement with Resurfacing - 2011
Project Number: 53W1086
Bid Due Date: 04/13/11
Bid Open Date: 04/20/2011
Estimated Start Date: 05/31/2011
Estimated Completion Date: 09/15/2011
Percent of Project Completed: 97.1 %
Contract Amount: $1,611,524.90
Project Contractor: SPEEDWAY SAND & GRAVEL INC
Construction Year: 2011
Construction Type: Sanitary
District:
PROJECT CONTACT:
Design Engineer: Steve Sonntag
Phone: 608-267-1997
Email: ssonntag@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Lauby, Paul
Phone: 261-9678