City of Madison Logo
Image: Public Works Header

PUBLIC WORKS CONTRACTS

CONTRACT NUMBER: 6716
CONTRACT: Packers Ave plan set 53W0321A
Percentage of Contract Completed: Not Available
Associated Projects:
  • STH 113 Pavement Replacement (53W0321)
PROJECT: STH 113 Pavement Replacement
Project Number: 53W0321
Bid Due Date: 01/01/11
Bid Open Date:
Estimated Start Date: 05/01/2011
Estimated Completion Date: 12/01/2011
Percent of Project Completed: Not Available
Contract Amount: Not Available
Project Contractor:
Construction Year: 2011
Construction Type: Street
District: 12, 15, 17, 18,
PROJECT CONTACT:
Design Engineer: Steve Sonntag
Phone: 608-267-1997
Email: ssonntag@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Lauby, Paul
Phone: 261-9678