Groveland Terrace

Last Updated: 05/17/2019

Construction Update

Contractor is finishing clearing and grubbing trees.  They plan to start installing sanitary sewer main mid week (May 21 or 22)

Road is open to local traffic only.

Project Description

This project is a proposed rural-to-urban project that will include the installation of sidewalk and curb and gutter as well as new pavement. Curb and sidewalk will be installed on both sides of the roadway and the roadway will be constructed to be 32'-wide from face of curb to face of curb. Sanitary sewer main and laterals will also be replaced with this project and new storm sewer will be installed. No water main replacement will occur with the project.

Project Limits

Groveland Terrace - Pflaum Rd. to Tompkins Dr.

Project Schedule

This project is anticipated to start in May and construction is expected to last approximately 3-4 months. In anticipation of construction, Madison Gas and Electric will be performing utility work on their gas facilities beginning in late March.

Public Information Meeting

A Public Information Meeting was held on Tuesday December 18th. The presentation from the meeting can be found here: PIM Presentation