John Nolen Drive

Monthly Meeting Reminder

Monthly construction progress meetings will be held IN-PERSON at the field office located at 701 E Washington Ave, Suite LL3 (former Brink Lounge) on the first Tuesday of every month at 11 a.m. starting on Tuesday, Nov. 4, 2025. The public is welcome to attend these meetings to learn about construction progress, upcoming work, as well as opportunity to ask questions of the construction team. Access to the field office building is located off of the back parking lot, which is accessed off of the S Blount St driveway. There will be door signs setup directing the public where to go to find the meeting location. 

Latest Update 11/7/2025

General Project Information

The John Nolen Drive project includes reconstructing John Nolen Drive and six bridges that span the causeway. New curb and gutter with a raised median separating northbound and southbound traffic will narrow traffic lanes to calm high traffic speeds. The Capital City Trail will be moved further from the roadway with the addition of three new bridge structures, increasing pedestrian safety and greenspace along the corridor. The trail will also be widened, increasing the capacity of the trail, with separate paths for bikes and foot traffic.

Project Schedule

Stage 1 Start Date: October 13, 2025

Anticipated Stage 1 Completion: Mid November 2025

Current Stage / Traffic Impacts – Stage 1

Work entails constructing temporary crossovers and temporary signals. Temporary storm sewer outfalls will also be constructed beneath the northbound lanes of John Nolen Drive.

  • Traffic restricted to one lane each direction
  • No left turns from Broom St to John Nolen Dr

Upcoming Stage / Traffic Impacts – Stage 2

Work entails reconstructing southbound John Nolen Drive, reconstructing three bridges on the causeway, and the Basset to Bedford pedestrian path.

  • Traffic restricted to one lane each direction on existing northbound lanes
  • No left turns from Broom St to John Nolen Dr
  • Nighttime full closures anticipated for bridge girder removal

Work Week of 11/10/25

  • The contractor will continue removing portions of the existing median islands to prepare for Stage 2 traffic.
  • Asphalt paving is scheduled for both crossovers and areas where medians have been removed
  • Storm sewer work will continue across northbound lanes of John Nolen Dr and the Capital City Trail.
  • Barges and cranes will be deployed to begin installation of cofferdams. This work will start at the northernmost bridge on the lake side.
  • No overnight work is anticipated

Work Week of 11/17/25

  • Traffic control devices, temporary pavement markings and temporary signals will be modified for Stage 2 traffic.
  • Cofferdam installation will continue.

Traffic/Pedestrian/Bike Impacts

  • A new temporary crosswalk on the north side of Broom St will be established. This will become the only crossing at Broom St and will remain until the project is complete.
  • The Capital City Trail will remain open; however, widths restrictions will be in place at isolated locations during standard hours. Trail users will be routed onto temporary pedestrian matting or existing roadway while the contractor installs storm sewer pipes across the path. Cyclists are encouraged to dismount from their bikes through these areas.
  • Motorist should expect a new traffic pattern the week of 11/17. All vehicles will use existing northbound lanes between Lakeside St and the Monona Terrace.

Please be alert when traveling along the John Nolen Drive corridor. Please note that some work is dependent on weather and may be subject to change. Thank you in advance for your patience throughout this project.

Events

Beginning November 15, Olin Park will host the annual Fantasy in Lights display. Access will remain available from both E Lakeside St and Olin-Turville Ct.

Welcome to the Holiday Fantasy in Lights - Fantasy In Lights

NECA and IBEW Local 159, along with many sponsors, bring you the 37th Annual Holiday Fantasy in Lights. 6 weeks of lights at Olin Park for all to drive through and enjoy at no charge. Over 60 lighted holiday displays to include tunnels and local scenes and treats. Lights on at Dusk- Candy Canes handled out at the exit 4:30 p.m. to 10 p.m. Lights on every single evening through Dec. 31.  

Contact Information

Mark Sponem, WisDOT – Project Manager

Email:  mark.sponem@dot.wi.gov

Dan Bauknecht, WisDOT – Project Engineer

Email:  daniel.bauknecht@dot.wi.gov

If you would like to be added or removed from the weekly update distribution list, please email your name and email address to  daniel.bauknecht@dot.wi.gov.

Progress Photos

John Nolen Drive Construction
John Nolen Drive Construction

10/31/2025 Update


The John Nolen Drive Reconstruction project will encompass a number of infrastructure design improvements along the causeway between E Olin Avenue and S Broom Street.

Phase One of the project includes the segment from E Lakeside Street to S Broom Street and has been selected for funding and is expected to be constructed in 2025-2026. Phase Two includes the segment from E Olin Avenue to E Lakeside Street and will be fully designed and constructed once funding is available.

Overview Exhibit
North Shore - Broom St Exhibit

Phase One (E Lakeside St to S Broom St) will include the following improvements:

  • Reconstruction of six bridges along the causeway, with 3 new separated bridges for the bike and pedestrian facilities
  • Lane configuration and cross section changes to urbanize the roadway and provide traffic calming
  • Expansion of the existing path to separate bike and pedestrian facilities
  • Shoreline reconstruction along Lake Monona
  • Reconstruction of storm sewer
  • Traffic signals and street lighting
  • Improvements to the North Shore Dr and S Broom St intersections
  • Coordination with potential future improvements identified in the Lake Monona Waterfront Master Plan

Map

John Nolen Drive

A number of exciting improvements are being considered, including:

  • Reconstruction of six bridges along the causeway
  • Lane configuration and cross section changes
  • Expansion of the existing path to separate bike path and pedestrian facilities
  • Shoreline reconstruction along Lake Monona
  • Reconstruction of storm sewer
  • Traffic signals and street lighting
  • Others to be determined through public involvement process

Listen to other John Nolen Drive Podcast Episodes: 

Business Resources

City's Road Reconstruction Business Guide

Project Schedule

This project will be planned and designed in coordination with the ongoing with the Monona Waterfront Design Challenge.

The process began in 2021 and is expected to run through 2026. It will include analysis of existing conditions, feasibility studies, and a robust community engagement process to inform preliminary and final designs.

  1. Preliminary Design Active

  2. Final Design Upcoming

  3. Construction Upcoming

Public Involvement

Public involvement is a central element to the planning process for this project. The public involvement process will utilize a range of tools including public meetings and workshops, small group meetings, surveys, event tabling and intercept interviews, and other effective methods proven to ensure the final designs are informed by the community.

Public Information Meetings

There are no upcoming events.

City Process Meetings

Transportation Commission

Presentation from the April 12, 2023 Transportation Commission:

Presentation from the May 24, 2023 Transportation Commission:

Roadway Geometry Approval/Preferred Alternative:  June 7, 2023

Board of Public Works

Roadway Geometry Approval/Preferred Alternative: June 21, 2023

Final design approval: March 12, 2025

Common Council

Roadway Geometry Approval/Preferred Alternative:  July 11, 2023

Final design approval: March 25, 2025

News Releases

Was this page helpful to you?