CONTRACT NUMBER: 6637
CONTRACT: Storm Sewer with Resurfacing East - 2011
Percentage of Contract Completed: 87.7%
Associated Projects:
  • Storm Sewer with Resurfacing East - 2011 (53W1114)
PROJECT: Storm Sewer with Resurfacing East - 2011
Project Number: 53W1114
Bid Due Date: 03/04/11
Bid Open Date: 03/11/2011
Estimated Start Date: 05/02/2011
Estimated Completion Date: 09/02/2011
Percent of Project Completed: 87.7 %
Contract Amount: $1,057,958.55
Project Contractor: RAYMOND P CATTELL INC
Construction Year: 2011
Construction Type: Storm
District:
PROJECT CONTACT:
Design Engineer: Sally Swenson
Phone: 608-266-4862
Email: sswenson@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Armstrong, Steve
Phone: 266-4914