CONTRACT: Reston Heights Path & Southwest Path wall repairs
Percentage of Contract Completed: 93.2%
Associated Projects:
  • Reston Heights Path & Southwest Path wall repairs (53W1225)
PROJECT: Reston Heights Path & Southwest Path wall repairs
Project Number: 53W1225
Bid Due Date: 06/17/11
Bid Open Date: 06/17/2011
Estimated Start Date: 08/17/2011
Estimated Completion Date: 09/30/2011
Percent of Project Completed: 93.2 %
Contract Amount: $38,471.00
Project Contractor: HOMBURG CONTRACTORS INC
Construction Year: 2011
Construction Type:
District:
PROJECT CONTACT:
Design Engineer: Tony Fernandez
Phone: 608-266-9219
Email: afernandez@cityofmadison.com
City Construction Engineer: John Fahrney
Email: jfahrney@cityofmadison.com
Phone: (608) 266 9091
Inspector: Hoel, Eric
Phone: 261-9270