Temporary Data Center Moratorium and Proposed Restrictions
Temporary Data Center Moratorium Background
On January 13, 2026, the Common Council voted to approve a temporary moratorium on issuing zoning approvals for new data centers with a floor area larger than 10,000 square feet. The moratorium only applies to data centers that are the principal or primary use of the property and is set to expire on January 24, 2027.
Right now, Madison's zoning code does not include a definition or any specific standards or regulations for "data centers." The "telecommunications centers" use in the zoning code has historically covered this type of business in Madison but is outdated due to the evolving nature and range of data centers across the United States and Wisconsin.
If the moratorium were to expire without new regulations being approved by the Common Council, almost any type of data center development could be allowed in areas where businesses operate with very few controls in place.
The moratorium was put into place to give City staff time to develop zoning and land use regulations for any potential future data centers.
Proposed Restrictions and Regulations
A set of data center restrictions and regulations will be introduced to the Common Council on November 24, 2026. This extensive list of new limits is the result of several months of research and work by City staff and feedback from the community during the moratorium.
Staff presented a draft framework of potential regulations during a series of meetings during the fall, and several of those recommendations have been adjusted as a result of that community feedback. Those changes to the initial draft framework include:
Reducing the maximum size of data center that would be allowed from 100,000 square feet in floor area to 75,000 square feet in floor area
Increasing the buffer between data centers of 50,000-75,000 square feet in floor area and residential areas from 300 feet to 500 feet
Adding a buffer of 300 feet between data centers of 50,000-75,000 square feet in floor area and other non-industrial areas to further limit where they could be located
Taken together, these regulations would significantly limit areas of the city where any data center between 50,000-75,000 square feet in floor area would be able to be located. Staff believes these size and location restrictions would effectively limit the amount of mechanical equipment used by these facilities to the point that they would not generate any more noise impacts than the mechanical equipment used by similarly sized facilities that already exist in Madison.
The regulations included in the proposed ordinance include:
Banning hyperscale data centers entirely
Banning data center campuses by requiring any data center of more than 10,000 square feet in floor area to be at least 1,000 feet away from another data center of that size and by capping to the total size of data center buildings per lot
Banning data centers of any size in any residential zoning districts
Restricting data centers of 50,000-75,000 square feet in floor area to only zoning districts for industrial uses (Industrial-Limited, Industrial-General, and Airport districts), along with the additional buffers mentioned above to further limit where they can be located
Restricting data centers of 10,000-50,000 square feet in floor area to only employment and campus institutional zoning districts (except for the Traditional Employment district)
Restricting data centers of 0-10,000 square feet in floor area to zoning districts for business and commercial uses (Mixed-Use, Commercial, Downtown, Urban, and Traditional Employment districts)
Banning data centers from being on the ground floor of a building in most parts of the city, preserving that space for better uses
Requiring the developer of any data center larger than 10,000 square feet in floor area to submit a Noise Mitigation Plan showing they will be able to comply with the City's noise ordinances before they are allowed to start building
A separate ordinance change would also significantly increase fines for any daily and recurring noise ordinance violations to further compel compliance with the noise ordinance.
More detailed and technical explanations of the proposed restrictions and regulations can be found in the memo to the Plan Commission and Common Council written by City staff and the proposed ordinance text.
The restrictions and regulations outlined in the proposed ordinance may change if policymakers recommend and approve amendments during the legislative process.